New Construction

NEW CONSTRUCTION PROJECTS

Construction of buildings or unit of a building in which the entire work is new or an entirely new addition. (Additional images may be viewed in the Photo Gallery below.)

Photos Coming Soon Message

Bayshore K-8 School

  • Project Type - Expansion
  • Anticipated Substantial Completion Date - 11-30-26
  • Current Status - Design Phase
  • Funding Source - Impact Fees
Overhead View of Cape Coral Technical College

Cape Coral Technical College

  • Project Type - Addition
  • Anticipated Substantial Completion Date - TBD
  • Current Status - Design Phase
  • Funding Source - Sales Tax
Photos Coming Soon Message

Cypress Lake High School

  • Project Type - ROTC Tower
  • Anticipated Substantial Completion Date - TBD
  • Current Status - Design Phase
  • Funding Source - Capital 
Pending Photos

Cypress Lake Middle School Rebuild

  • Project Type - New School
  • Anticipated Substantial Completion Date - 6-1-26
  • Current Status - Design Phase
  • Funding Source - TBD
Amanecer Elementary - June 2023

Amanecer Elementary School (Elementary "J")

  • Project Type - New School
  • Substantial Completion Date - 7-14-23
  • Current Status - Close-Out Phase
  • Funding Source - Capital
Artist's Rendering of the Rebuilt Franklin Elementary School

Franklin Park Elementary

  • Project Type - Rebuild
  • Anticipated Substantial Completion Date – 7-1-24
  • Current Status – In Construction Phase
  • Funding Source - COPs
Artist's Rendering of G Weaver Hipps Addition

G. Weaver Hipps Pre-K

  • Project Type - Addition
  • Anticipated Substantial Completion Date – 6-12-24
  • Current Status – In the Construction Phase
  • Funding - Capital
Pictures Pending for Innovation School

Innovation School

  • Project Type - New School
  • Anticipated Substantial Completion Date - TBD
  • Current Status - Design Phase
  • Funding Source - Capital
Portable Installation at Hector Cafferata

Hector A. Cafferata, Jr. Elementary School

  • Project Type - Portables Installation
  • Completion Date - 12-10-22
  • Current Status - Completed
  • Funding Source - Hurricane Ian Funds
Photos Coming Soon Message

"L" Elementary School

  • Project Type - New School
  • Anticipated Substantial Completion Date - TBD
  • Current Status - Design Phase
  • Funding Source - TBD
MM Middle School Building Addition

Lehigh Acres Middle School

  • Project Type - Addition
  • Anticipated Substantial Completion Date - 3-1-23
  • Current Status - Close-Out Phase
  • Funding Source - Capital
Photos Coming Soon Message

NNN High School

  • Project Type - New School
  • Anticipated Substantial Completion Date - 6-29-28
  • Current Status -  Design Phase
  • Funding Source - Capital
Artist's Rendering of OO School

OO Middle School

  • Project Type - New School
  • Anticipated Substantial Completion Date - 4-16-28
  • Current Status - Design Phase
  • Funding Source - Capital
New Building Transportation East Buckingham

Transportation East (Buckingham)

  • Project Type - New Facility
  • Anticipated Substantial Completion Date - 1-30-23
  • Current Status - Completed
  • Funding Source - Capital